SAP S/4HANA Administration
Product Availability & Maintenance Strategy
19 flashcards · answers and spaced-repetition review in the KnowCard app
A consultant scopes an 'EHP upgrade' project for an S/4HANA system. Why is that scope wrong from the start?
S/4HANA 2022 is in mainstream support for 'five years after the release year.' What concrete end date does that give you, and why doesn't SAP's 2040 commitment let you relax about it?
Before scheduling an upgrade to S/4HANA 2022, which PAM tab tells you whether your current release is even a valid starting point, and what is the floor?
Mainstream maintenance for your release ends in three months and the upgrade won't finish in time. Are you actually out of support, and what is the cost trade-off?
In PAM, which tab and Product Instance setting lists the minimum SAP GUI version for S/4HANA 2022, and what version is required?
Within the ~2-year initial period after GA you can take an FPS instead of an SPS. Of the new features it ships, which kind silently changes behavior unless you act, and which is safe?
In PAM, which selection and tab give you the minimum SAP HANA version and supported OS for S/4HANA?
What single document must you read before applying any support or feature package stack, and why isn't the stack self-explanatory without it?
S/4HANA 1709, 1809, and 1909 had staggered mainstream end dates — so do their extended-maintenance windows also end on different dates?
Why does SAP bundle support packages into tested SPSes instead of letting you apply individual SPs component-by-component?
A new team member can't open the Product Availability Matrix to check supported platforms. What is the most likely blocker, and what is PAM actually for?
Name the three delivery vehicles in the S/4HANA release strategy — and the one veterans wrongly add from the ERP world.
A colleague plans to apply the latest quarterly stack and assumes it only fixes bugs, like every SPS. Why is that assumption dangerous if the stack is an FPS?
Why is it wrong to expect a single support package to patch the entire S/4HANA software stack at once?
A stakeholder worries about long-term investment protection for on-premise SAP S/4HANA. What long-range maintenance commitment has SAP made?
For SAP S/4HANA Cloud, how are functional updates delivered between the two yearly product versions, and how are they numbered?
A team assumes SAP S/4HANA still ships yearly with 5-year maintenance and is caught off guard that S/4HANA 2021 maintenance already ends in 2026. What is the current release model?
A customer running S/4HANA on premise asks how often they are forced to upgrade and how long a given version keeps getting support. What is the current answer?
On S/4HANA Cloud (Public) an admin wants to schedule around upgrades the way they used to plan for quarterly drops. Why does that plan no longer fit, and how much control do they actually have over the dates?